Menu
  • Home
  • Breaking News
  • Feature
    • Arts
    • Astrology
    • Business
    • Community
    • Employment
    • Event Stories
    • From the Pioneer
    • Government
    • Letters to the Editor
    • Non Profit News
    • Obituary
    • Public Safety
    • Podcast Interview Articles
    • Pioneer Pulse Podcast: Politics, Palette, and Planet – the Playlist
  • Weather
  • Guest Column
    • Perspectives
    • Don Backman Photos
    • Ardent Gourmet
    • Kitchen Maven
    • I’ve been thinking
    • Jim Heffernan
    • The Littoral Life
    • Neal Lemery
    • View From Here
    • Virginia Carrell Prowell
    • Words of Wisdom
  • Things to do
    • Calendar
    • Tillamook County Parks
    • Tillamook County Hikes
    • Whale Watching
    • Tillamook County Library
    • SOS Community Calendar
  • About
    • Contribute
    • Advertise
    • Subscribe
    • Opt-out preferences
  • Post Submission Test
  • Search...
Menu

Contaminated groundwater issue causes short term delay in downtown project; Additional lanes to open after Memorial Day; project is still on schedule to be completed by late 2018

Posted on May 3, 2017April 3, 2020 by Editor

TILLAMOOK— A goal to open two lanes of U.S. 101 in both directions by Memorial Day will be delayed until later this summer because of a significant amount of contaminated groundwater that was discovered during excavation at the site of the U.S. 101/OR 6 Project in Tillamook.

To address the problem, the contractor will need to perform extra work, pushing back the first deadline for work accomplished.    The plan was to have the east half of the Hoquarton Slough Bridge finished by Memorial Day with two lanes open on U.S. 101 in both directions.  Now, that will not happen until later in the summer.

The contractor is currently working on the east half of the bridge with one lane open in both directions.  The goal is to have one additional southbound lane open before June 9. Also, after Memorial Day, the contractor will have two lanes open on Pacific Avenue in Tillamook.  Overall, the project is still on-schedule to be completed by the end of 2018.

Background:  During excavation earlier in the winter, a significant amount of contaminated groundwater was discovered in the area just east of U.S. 101 and south of the slough.  Heavy and consistent rainfall throughout the winter and spring have added much more water to the site and further complicated the treatment process.   The contractor and ODOT needed to determine how to address the problem, and the contractor has been forced to concentrate resources on this issue, thereby putting the bridge construction behind schedule.

A company that specializes in treatment of contaminated water has provided a treatment system approved by the Department of Environmental Quality.  At the construction site, two 20,000 gallon tanks are used to pump out the contaminated water, filter and treat it and discharge it back in to the slough.  The system only treats the water.  It is not designed to clean up the site.

Prior to the start of construction, ODOT drilled test holes at the construction site and suspected that there might be contamination issues.   The history of the site included an old sawmill and
other businesses that could have been the source of the contamination over time.  However, ODOT did not expect the extent of and the quantity of contaminated water that was discovered.

Once the site has a chance to dry out this summer excavation activities should get back to normal and there will be much less contaminated water to treat.

ODOT is working with the contractor on a plan that will accelerate work and minimize any additional schedule impacts.   There is enough time in the overall schedule to get all the necessary work done by the end of 2018, as originally planned.

The Oregon Transportation Commission (OTC) has approved an additional $2.5 million of mostly unexpended Jobs and Transportation Act funds for treatment of the contaminated water and for accelerating the work.

ODOT and the contractor will make attempts to open the extra lanes as soon as possible.

When the project is finished, travelers on U.S. 101 through downtown Tillamook will experience wider streets, a safer and more intuitive U.S. 101/OR 6 intersection, a new four-lane bridge that will include bike lanes, wider sidewalks, viewing platforms and other aesthetic enhancements.

Featured Video

Slide Contribute SUBSCRIBE

Tillamook Weather

Tides

Tillamook County Pioneer Podcast Series

Tillamook Church Search

Cloverdale Baptist Church
Nestucca Valley Presbyterian
Tillamook Ecumenical Service

Archives

  • Home
  • EULA Privacy Policy
  • Contact
  • Opt-out preferences
  • Search...
Share on facebook
Facebook
Share on pinterest
Pinterest
Share on twitter
Twitter
Share on linkedin
Linkedin
Catherine

Recent Posts

  • Grove avenue closed in Tillamook for maintenance

    May 10, 2025
  • Astoria Farmers Market new, outdoor location with parking, with great Riverwalk access

    May 10, 2025
  • WORDS OF WISDOM: Boycotts and Protests in our Community Garden

    May 9, 2025
©2025 | Theme by SuperbThemes

Manage Cookie Consent
To provide the best experiences, we use technologies like cookies to store and/or access device information. Consenting to these technologies will allow us to process data such as browsing behavior or unique IDs on this site. Not consenting or withdrawing consent, may adversely affect certain features and functions.
Functional Always active
The technical storage or access is strictly necessary for the legitimate purpose of enabling the use of a specific service explicitly requested by the subscriber or user, or for the sole purpose of carrying out the transmission of a communication over an electronic communications network.
Preferences
The technical storage or access is necessary for the legitimate purpose of storing preferences that are not requested by the subscriber or user.
Statistics
The technical storage or access that is used exclusively for statistical purposes. The technical storage or access that is used exclusively for anonymous statistical purposes. Without a subpoena, voluntary compliance on the part of your Internet Service Provider, or additional records from a third party, information stored or retrieved for this purpose alone cannot usually be used to identify you.
Marketing
The technical storage or access is required to create user profiles to send advertising, or to track the user on a website or across several websites for similar marketing purposes.
Manage options Manage services Manage {vendor_count} vendors Read more about these purposes
View preferences
{title} {title} {title}