“The contractor is continuing to construct a jetty crest haul road for trucks to deliver armor stone for repairs at the seaward (west) end of the jetty. The repairs will include re-establishing a jetty head past the current, visible end of the jetty (where the jetty is currently submerged) and also repairs to the trunk of the jetty adjacent to the head. Placement of the armor stone associated with these repairs is expected to start within the latter half of the month of July.”
Matthew Craig, P.E., Project Manager for Tillamook South Jetty Repairs
We will provide further updates as we get them. The public can sign up to receive construction updates including when work will begin, road closures and other public safety messages by emailing the USACE at cenwp-construction@usace.army.mil