OIOpublisher In an effort to catch up with the schedule, the project crews have been working six-tens in most locations. Westwind, the concrete flatwork subcontractors, will be jamming on the sidewalks with…
Category: Oregon Dept of Transportation (ODOT)
Highway 101/6 Project Update
After extended discussion, and multiple schedule revisions, at this week’s ODOT project team meeting, the contractors and agency partners concluded that, in order to expedite the Pacific Avenue sidewalk work, additional crew…
Highway 101/6 Project Update – March 31, 2017
Oregon spring break has thrown more than usual commotion into the traffic mix and next week’s Washington break may add even more, particularly if the weather shows a couple of strands of…
Highway 101/6 Project Update
When Governor Kate Brown came to town on Wednesday March 15th to view the progress of the 101/6 Highway Project, the rain provided a seamless backdrop curtain to the jackhammers and sawcutting…
Highway 101/6 Project Update
From Tillamook Chamber of Commerce The time is fast approaching for us all to cross the bridge to our Rendezvous. On Friday March 10th, the long-lingering sidewalk construction on Pacific Avenue between…